Baltimore City · 21218

2200 SAINT PAUL ST

Property watching is a Pro feature. Join the waitlist to get new permits, violations, and inspections on this property in a daily email digest.

Total assessment
$2,672,400
Land use
Commercial (C)
Year built
1886
Last sale
Mar 24, 1890

Assessment

OwnerLOVELY LANE UNITED
Land useCommercial (C)
Total assessment$2,672,400 (cycle 2026)
Last saleMar 24, 1890
Year built1886
ZoningR-8
Vacant

Permits

16
TypeDescriptionCostIssued
COM2023THE ADDITION OF OPERABLE DECORATIVE STEEL SECURITY GATES TO THE ST. PAUL AND 22ND STREET ENTRY LOGGIAS AS PER PLANS AS PER CODE.$50,000Aug 9, 2023
COM2023REPLACE TWO EXISTING ILLUMINATED CHURCH SIGN WITH TWO NEW SIGNS WORK TO INVOLVE REPLACEMENT OF EXISTING SIGNS, EXISTING POSTS WILL REMAIN, FOR THE LARGER SIGN WE ARE USING THE EXISTING POSTS - JUST REMOVING THE OLD SIGN AND REPLACING WITH NEW, FOR THE SMALLER SIGN WE ARE REMOVING THE OLD SIGN AND CHANGING THE SIGN ON EXISTING POSTS, AS PER PLANS AS PER CODE.$23,840Jul 27, 2023
COM2023INSTALL (2) # PLUMBING FIXTURES AS PER CODE.$1,000Jan 23, 2023
COM2022AMEND PLAN #2021-2166 PERMIT PERMIT COM2021-03014 ISSUED 5/12/2022 TO CHANGE SOUTHWEST SHAFT AT STAGE TO REMOVE SHAFT RATING AND ADD RATING AT SINGLE FLOOR PENETRATION, REVISION TO DETAIL B2 ON SHEET A-501 ONLY AS PER PLANS AS PER CODE. (PROPOSED CHANGE WAS DISCUSSED WITH MR. EAMES PRIOR TO SUBMISSION)$0Oct 10, 2022
COM2022AMEND PERMIT: ADD HVAC CONTRACTOR . (ORIGINAL PERMIT:COM2021-03014:WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.) Original Permit Description:(COM2021-03014) WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.Jul 2, 2022
COM2022AMEND PERMIT: ADD PLUMBER AND GAS CONTRACTOR . (ORIGINAL PERMIT:COM2021-03014:WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.) Original Permit Description:(COM2021-03014) WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.May 18, 2022
COM2022AMEND TO ADD ELECTRICAL CONTRACTOR: (ORIGINAL PERMIT:COM2021-03014:WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.) Original Permit Description:(COM2021-03014) WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.May 18, 2022
COM2021WITHIN AN EXISTING BUILDING WITH LIMITED WORK AREAS INCLUDING THE FELLOWSHIP HALL, LIMITED PORTIONS OF THE BASEMENT AND SECOND FLOOR, AND THE ROOF, WORK IN FELLOWSHIP HALL INCLUDES A NEW ACCESSIBLE LIFT FOR STAGE, UPDATED FINISHES, AND INSTALLATION OF VENTILATION AIR AND COOLING SYSTEMS, ON THE SECOND FLOOR EXISTING DUCT WORK WILL REMAIN AND TIED INTO NEW SYSTEM, MODIFICATIONS TO THE EXISTING ELECTRICAL SERVICE WILL OCCUR IN THE BASEMENT TO COMBINE TWO EXISTING SERVICES AND BRING THEM INTO CODE COMPLIANCE, ASSOCIATED DUCTS, PIPING, AND DUCT PENETRATIONS WILL BE INSTALLED, ROOF WILL BE REINFORCED AND REPLACED TO ACCOMMODATE THE NEW MECHANICAL SYSTEM (INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE. NO EXITS OR EXIT ACCESS WILL BE REMOVED) WALL MODIFICATION OCCURS ONLY AT NEW HVAC CHASES AND AT MAIN ELECTRICAL ROOM AS PER PLANS AS PER CODE.$424,952May 12, 2022
COM2021AMEND PERMIT: ADD ELECTRICAL CONTRACTOR .(ORIGINAL PERMIT:COM2020-02868:FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.) Original Permit Description:(COM2020-02868) FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.Feb 17, 2021
COM2021AMEND PERMIT: ADD HVAC CONTRACTOR .(ORIGINAL PERMIT:COM2020-02868:FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.) Original Permit Description:(COM2020-02868) FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.Feb 11, 2021
COM2021AMEND PERMIT: ADD PLUMBER CONTRACTOR .(ORIGINAL PERMIT:COM2020-02868:FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.) Original Permit Description:(COM2020-02868) FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.Feb 11, 2021
COM2020FOUR NEW TOILET ROOMS WILL BE ADDED TO THE EXISTING BUILDING; 2 ACCESSIBLE, 2 NON-ACCESSIBLE, A NEW ADA ACCESSIBLE EXTERIOR RAMP WILL BE INSTALLED ALONG THE NORTH FAÇADE AND WILL INCLUDE RAISING THE EXISTING PORCH LEVEL TO FIRST FLOOR LEVEL AND STAIRS AT THE WEST END TO MAINTAIN ACCESS TO THE EGRESS DOORS IN THE CENTER OF THE NORTH FAÇADE. INTERIOR EGRESS TRAVEL PATHWAYS WILL NOT BE MODIFIED UNDER THIS SCOPE OF WORK, NO EXIT OR EXIT ACCESS WILL BE REMOVED, MEP SYSTEMS WILL BE TIED INTO EXISTING AS PER PLANS AS PER CODE.$400,000Feb 10, 2021
COM2019replace 2 hvac units with new units with humidity control for museum. add receptacles in partitions. replace fluorescent fixtures with led in basement. relocate 3 switches. install 2 fans and a receptacle in gym. install (8) # branch circuits/feeders , (40) # fixtures/devices, (6) # low voltage as per code.replace 2 ac unit 3ton.$12,000Aug 27, 2019
COM2019install distribution system (reconstruction of ductwork), as per code. (direct replacement in the same size, capacity, and location)$8,000Aug 14, 2019
COM2019replace (2) 48000 btu air-con system, heat pump as per code.$21,000Aug 1, 2019
COM2019scope of work:--interior alterations--reworking existing walls adding hvac and electric. separate trade permits will be required as per plans as per code$14,800Jul 31, 2019

Violations

0

No violations on record.

Inspections

0

No inspections on record.

Nearby recent activity

Records marked with * are matched by address, not a direct account link. Data is informational only.

Data freshness: city-311: 2026-07-12; city-ecb-citations: 2026-07-12; city-housing-inspections: 2026-07-12; city-permits: 2026-07-12; city-real-property: 2026-07-12; city-vbn: 2026-07-12; county-permits: 2026-07-12; sdat-properties: 2026-07-12;

Official sources: Maryland SDAT, Baltimore City permits.